Data center growth puts unprecedented pressure on power grids
Data center builds typically have timelines of 18 to 24 months, gas and renewable power plans have timelines of three to five years, and new transmission development can take seven to ten years. In fact, it’s the power transmission grid that’s often the biggest constraint, the research firm says, more even than the power generation capacity.